
JKW Project Reseeding Area and Work Crew - October 2006
10/15/06:
I do want to extend
special thanks to Mike and David for their hard work this past Saturday
helping to clear and re-cover "Area B" of the JKW site. This project proved
to be a lot more difficult and time-consuming than I ever would have
expected, but I think we did a satisfactory job. The left side had not been
dug out as thoroughly as the right, and we found a number of sizeable
rhizomes that had to be removed. There also were a lot of JKW roots and
plants that had been tossed on top of the plastic during previous removal
sessions and it took a considerable effort to clean this material up and
cart it over to the refuse pile.
We used all of the remaining rolls of plastic sheeting
that Sandra and I purchased last summer (five in all) to re-cover Area B --
four vertically and one horizontally at the top of the bank by the fence. It
might be noted for the record that we ended up discarding most of the old
sheets, as they were hole-ridden and the plastic had become brittle. We did
reuse one for additional cover on the refuse pile (which has now become much
larger), and another to fill a gap at the top left of Area B.
The part that we planted a month or so ago (I will call
it "Area A") is growing in nicely and should be in good shape for the
winter. Mike, David and I had some discussion about seeding Area B in the
spring; but on further reflection, now that we have done all this work, I
firmly believe we should leave that area covered through next summer and
plant again in the fall. - JB
10/10/06:
On Monday afternoon,
I went back to the JKW site for several hours with the weed whacker provided
by Mike and did a very thorough cleanup of essentially all of the knotweed
in the area. This should complete the JKW clearing work for the season. I
also cleaned up and removed all the trash we had gathered during our recent
work with the exception of the large steel rod and large steel bar, which I
was afraid our Lexington trash collectors might not take. Before I did the
clearing work, I took some photographs which I will pass on to David after
they are developed, but it was late enough in the day that the lighting on
the bank was not terrific, so they may not come out too well.
- This means that the only tasks left to be done to prepare this site
for the winter are:
- Cleaning up and re-covering the western half of the dig-and-cut area
- Removing the steel scraps
- Moving the new JKW root pile under the tarp, and
- Cleaning up and bringing inside for winter storage the tools we have
been keeping under the tarp, including a pick mattock and two weed
cutters
After looking more closely at the western
portion of the site yesterday afternoon, I now think this will be a bigger
project than I had anticipated. There are a lot of holes and gaps in the
sheeting on that side, and I don't think the JKW rhizomes were cleared out
as thoroughly when the work was originally done so there is quite a bit of
new growth. To do this right, we really should pull up all of the existing
plastic, dig out shoots and root systems wherever we can find them, and then
re-cover thoroughly, using new plastic sheeting where the old sheeting has
been torn or ripped. This will probably be a two or three hour project. I
have no immediate plans to do this work, but it probably should be done
before it gets cold and the ground freezes, i.e., before mid-November. - JB
7/26/06:
Here is a very brief JKW update.
On Sunday afternoon, I was finally able to get the time
to visit the JKW site with Mike's gas-powered weed whacker. Luckily, Don
happened to be there as well. (It was good to know that someone would be
able to call for help if I severed a finger or toe.) After some Keystone
Cops efforts to get the thing started, I finally discovered the hidden
on-off switch located on the handle and had no trouble after that.
In less than half an hour, I was able to cut down the
entire stand of JKW, by then about 3-6 feet high depending on the location,
to the east of the covered area. The results were a bit rough, but it was
much faster than doing it by hand.
Don and his crew had taken care of the JKW on the west
side of the plastic a week or two earlier. They had also pulled up JKW
growing between the cracks of the plastic and about half of that growing
along the bottom of the bank between the plastic and the marsh. There was
still a pretty healthy stand of JKW growing at the bottom of the bank, and I
was able to dig this out by the roots pretty quickly with the mattock.
So I think we have the area pretty much in control at
this point, and it should be good for another few weeks at least. At some
point I still want to remove the plastic, dig out remaining rhizomes and
recover thoroughly. I'm not sure when I'll get to that. - JB
6/25/06:
The JKW plot is getting out of control. The last time I was there
was Wednesday, June 21. If no more work has been done since then, here is
the current status of the three sub-plots:
1. East of the black plastic (managed by John): This is
probably the most in control of the three, but the JKW was up about three or
four feet on 6-21.
2. The black plastic area: JKW has grown tall in the
gaps between the sheets of plastic and from under the plastic on the west
side (maybe the east, too, I'm not sure). A lot of pulling or cutting is
needed, and the plastic needs to be adjusted. Since it is growing all along
the wetland side of the plastic, it seems we need another sheet or sheets
there after the thick JKW is removed. From all the JKW growing up in the
gaps between the sheets of plastic, it seems we need much more overlap
between sheets.
3. The west end of the plot (managed by me): Since my
last report to you, I've worked an additional four times, a little over an
hour each time. I've accomplished a lot, but with rainy days and some
too-hot-to-work days, it got a bit away from me. This past Wednesday I took
down nearly all the very tall JKW down low on the slope, and I worked on a
lot of the shorter plants. But (guess what?) it keeps growing fast. Now
there is still quite a bit at the 3 to 4 foot height which I haven't taken
care of yet, and probably some taller than that. Unfortunately, my wrist and
elbow are giving me sharp reminders to take it easy, so I'm going to have to
use less "enthusiastic" techniques in the coming weeks. Also, I will be
out-of-town from Thursday, June 29 until late on Wednesday, July 5. I am
hoping someone else can also help with this. A lot can be accomplished in a
single hour. - DM

Student Work Crew from the Waldorf High School - April 2006
4/27/06:
It was a great day out in the JKW fields.
The students worked really hard for about 3 hours, but I am afraid we did
not get the whole plot finished. The covered plots were looking pretty good,
but we still dug up more rhizomes.
We uncovered, cleared, and recovered 4 sheets worth
which was more than half, maybe almost 2/3’ s of the area. We started on the
5th section, but didn’t have time to complete it and it was the worst as far
as having rhizomes, so we covered it up with an old sheet again and that is
where we need to resume work. We added our newly dug rhizomes to the pile
under the tarp. The girls were worn out after a while working on the JKW, so
they actually were happy to sit and pull up the garlic mustard in the cut,
cut, cut plot and at the top of the covered area near the fence. They
gathered 3 bags full. Several people stopped to thank us over the course of
the morning. - SR
8/2/2005:
This early evening Barbara Strell, Sarah Garner, and I worked on the JKW
site for somewhat over an hour. A man named Kenny joined in after some
encouragement from us. Someone else had already cut down the
three-foot-high JKW growing up between the black plastic and the pile
under the tarp -- thank you.
The four of us worked on the following:
1. We pulled up some of the short new shoots just west of the tarp.
2. Over on the other side of the plastic, we cut back the knotweed
along more of the margin with the marsh, right back to the purple
loosestrife, and hauled the stalks up the hill where they will get more
sun. We also pulled up some of the young new shoots just up the slope
from there.
3. We lifted up the tarp and found that the stuff under it is really
foul, almost completely brown and just a few thin, whitish anemic stalks
that don't amount to much. My suggestion at the last meeting of hauling
that stuff out to where the sun can get at it seemed a less appealing
idea tonight, and we didn't get into it. However, it may be the best
way to get this stuff to burn eventually. If we do it, we will probably
need garden spades and wheel barrows, at least for some of it.
Sarah and Barbara said they can do some additional work in the near
future, which is great. I will be out of town from this Thursday
evening until Wed morning of next week, so it will be a while before I
can do more. [Don]
With many hours of volunteer work the area has been cleared
of JKW. But shoots continue to come up from the underground rhizomes and
the area will require continued vigilance and work before the JKW can be said to
be controlled. The picture below shows the view from the bikeway on August 10.
The area in AGM along the Eastern end of the Minuteman
Bikeway has been heavily infested with Japanese Knoweed which has choked out all
other vegetation and blocked what was once a very attractive view of the
Meadows.